The scope on Johnstaff’s current engagement in November 2021 is based on the approved Business Case June 2022. The proposed development will provide Core 35 facilities to NNPS, catering for current enrolment (up to 740 students) and Stream 7 facilities to Narrabeen Sports High School (NSHS), catering for current enrolment (up to 990 students). This is to future-proof the site by enabling capital works in the future in the case of demand exceeding projections.
Provision of Project Management Services for Phases 3 andoptional Phases 4 - 9, including delivery of Schematic Design, Contractor Procurement, Detail Design, Construction, Commissioning and Handover.
Budget overrun with the shortlisted tenders due to market escalation. Johnstaff undertook a cost reduction exercise which was necessary to mitigate the cost risks associated with Tender returns and Post Tender Clarifications responses. The site posed a ground contamination risk associated with proposed foundation works and associated soft and hard landscaping.Johnstaff has worked closely with SINSW to transfer the risk by careful collation of RFT documents.